Former Alcoa East site, Massena · St. Lawrence County

Massena’s exemption remains a question

What changed

NCPR reported October 7 that NYDIG/NCCS believes its proposed 635 MW campus may sit outside New York’s permit pause. The state had not confirmed that position.

Changed Oct 7, 2026 90% confidence 1 public source

Why it matters

The answer could affect other previously initiated proposals.

Watch next

Written state determination; the October 21 board meeting has no confirmed project agenda.