Power signal
Monrovia · Morgan County
Google’s Morgan County campus clears a major utility gate
What changed
Indiana regulators approved AES Indiana’s large-load growth plan on October 7. AES says the framework serving Google’s Morgan County campus makes large customers cover new service costs and projects more than $770 million of benefits for existing customers over 15 years.
Changed Oct 7, 2026 90% confidence 1 public source
Why it matters
The utility arrangement has moved from proposal to approval. Its projected customer benefits still depend on delivery, and this decision does not establish that the campus or all supporting generation is complete.
Watch next
Implementation filings and the timing of grid and generation work.