Power signal
Hilliard · Franklin County
Hilliard ends its AWS fuel-cell permit appeal
Hilliard withdrew its appeal of Ohio EPA's permit to install for a 72.9 MW solid-oxide fuel-cell facility at the AWS Scioto Darby Road campus. The City says the 228-unit Bloom Energy installation is intended to serve on-site data-center electricity demand and will be owned and operated by Ohio Power Company, an AEP subsidiary.
Why it matters
The City says it has exhausted the available appeal path. That removes a defined state-permit challenge from this power-development track, while leaving local safety review and the facility's operating details important to watch.
Watch next
Norwich Township's safety and technical review · installation and operating milestones · any further Ohio EPA or utility filings · disclosure of the on-site power arrangement