DATA CENTER ATLASGREAT LAKES
Paused / Contested

Gibraltar, MI · Wayne County

Raeden Gibraltar Data Center

Raeden is pursuing a 100 MW campus at the former McLouth Steel property and has sued Gibraltar over the city's one-year data-center moratorium.

MichiganFacility location
Power100 MW proposed
Operator / developerRaeden
Site / phaseContested
UtilityDTE Energy context; current interconnection details are not public

Project timeline

1 update
Proposal paused or denied

Raeden and Wayne County both identify the Gibraltar proposal. The moratorium prevents this from being represented as an approved or operating facility.

Hotlist signal history

1 reviewed change