Van Buren Township Planning Commission voted 5-2 to grant preliminary approval for Case 25-041.
Van Buren Township, MI · Wayne County
Google / Panattoni Project Cannoli
Google and Panattoni are advancing a three-building, 1 GW campus in Van Buren Township. MPSC approved the project-specific DTE supply and clean-capacity agreements; service is expected in December 2027 and maximum load in December 2028, while construction and operation remain unconfirmed.
Project timeline
Google said it is evaluating a Van Buren Township data-center site and partnering with DTE Energy.
Case U-22058 approved the 20-year primary supply and clean-capacity agreements; future service dates do not establish construction.
The project remains proposed while final site-plan and environmental approvals proceed through separate reviews.