Permitting
Forward Township · Butler County
Forward Township receives amended Misty Hollow Energy & Data Campus plans
What changed
Forward Township received the developer's resubmission for the proposed Misty Hollow Energy & Data Campus on October 15, including revised preliminary land-development and stormwater materials. The plans remain under review; the resubmission is neither a township approval nor construction authorization.
Changed Oct 15, 2026 93% confidence 1 public source
Why it matters
The amended filing restarts a substantive local-review phase for a paired energy-and-data proposal in Butler County and puts the adequacy of stormwater and engineering responses at the next gate.
Watch next
Township engineer review · rescheduled Planning Commission meeting · Board of Supervisors action before the statutory review deadline · agency comments