Data Center Atlas Intelligence LayerSignals are concise, sourced changes captured as data-center projects, power, policy, and local conditions evolve across the Great Lakes.
Project watch
Van Buren Township · Wayne County
Van Buren Township schedules final Project Cannoli site-plan review
What changed
WGVU reported that Van Buren Township officials were scheduled to take final site-plan review for Google's proposed Project Cannoli data center during the week of October 12. The source did not establish a final approval; the project remains proposed pending the Township record and any remaining permits.
Changed Oct 12, 2026 88% confidence 1 public source
Why it matters
A final local site-plan decision is a material entitlement gate for the proposed Michigan campus, but a scheduled review is not approval or construction authorization.
Watch next
Planning Commission minutes and vote · final conditions · state and local permit filings · construction timetable