Data Center Atlas Intelligence LayerSignals are concise, sourced changes captured as data-center projects, power, policy, and local conditions evolve across the Great Lakes.
Project watch
Homer City · Indiana County
Indiana County begins outside engineering review of AWS Homer City master plan
What changed
Reporting on October 14 said Indiana County retained Stiffler-McGraw to review Amazon Data Services' preliminary master land-development plan for the Homer City Energy Campus. The proposed plan describes a phased multi-site data-center campus; it remains under local review and is not approved construction.
Changed Oct 14, 2026 92% confidence 2 public sources
Why it matters
An external technical review is a concrete next gate for one of Pennsylvania's largest proposed power-and-compute redevelopments, with land-use, generation, water, and community-review implications still unresolved.
Watch next
Engineer review findings · Planning Commission action · township approvals and waivers · DEP and power-infrastructure records