Developer appeals Upper Merion rejection of five-site campus

What changed

Developer Brian O'Neill filed land-use appeals after Upper Merion Township rejected a proposed five-site, 4.6-million-square-foot data-center campus. The appeals are pending and do not reverse the township's rejection.

Changed Sep 18, 2026 97% confidence 1 public source
Get weekly intelligence

Why it matters

The litigation keeps a very large campus alive while testing how existing warehouse zoning applies to data centers.

Watch next

Court docket · township response · stay or remand · revised applications