Developer appeals Upper Merion rejection of five-site campus
What changed
Developer Brian O'Neill filed land-use appeals after Upper Merion Township rejected a proposed five-site, 4.6-million-square-foot data-center campus. The appeals are pending and do not reverse the township's rejection.
Changed Sep 18, 2026 97% confidence 1 public source
Why it matters
The litigation keeps a very large campus alive while testing how existing warehouse zoning applies to data centers.
Watch next
Court docket · township response · stay or remand · revised applications