DATA CENTER ATLASGREAT LAKES
Data Center Atlas Intelligence LayerSignals are concise, sourced changes captured as data-center projects, power, policy, and local conditions evolve across the Great Lakes.

Power signal

City of Port Washington · Ozaukee County

ATC refiles $2.5B-$2.7B Port Washington grid package

What changed

American Transmission Company refiled its revised eastern Wisconsin transmission and substation application after regulators required a restart. Reporting places the revised cost at $2.5 billion to $2.7 billion. The filing restarts review; it is not construction approval.

Changed Sep 14, 2026 99% confidence 1 public source
Get weekly intelligence

Why it matters

The grid package is critical to serving the $15 billion Port Washington campus and now carries a materially larger cost and a fresh regulatory clock.

Watch next

PSC completeness review · route changes · cost allocation · final approval