Permitting

Limerick Township · Montgomery County

Limerick campus enters phase-by-phase review

What changed

Limerick Township listed a September 8 continuation for MCD 7's eight-building campus and separate pending applications for Phase 1 and Phase 2. Phase 1 covers one approximately 300,000-square-foot building; Phase 2 covers the remaining seven buildings and major electrical infrastructure.

Changed Sep 8, 2026 99% confidence 1 public source

Why it matters

The phase-specific filings turn a broad 191-acre concept into measurable approval and procurement steps. They expose the first building, generator and chiller counts, substation scope and later-campus sequence without assuming construction is approved.

Watch next

Published outcome of the September 8 continuation · hearing dates for CU 26-05 and CU 26-06 · switching-station review · public water, sewer and road-relocation conditions